District |
Project # |
Donor |
Implementer |
Project |
Scope of work |
NWS&DB Phase |
Budget Identified (Million US $) |
Remarks |
| 1 |
Ampara |
AMP/03 |
AmCross |
GRC |
Ninthavur distribution improvement & connection to resettlement in Arasadithottam |
Connection from Kondawattuwana Irrigation tank laying of transmisson to resettlement areas in Arasadithottam |
II |
7 |
Final draft of the project proposal has been sent to AmCross HQ - Washington, for their comments & which is exted to get within one month time. This was initialy prepared by German Red Cross. |
| 2 |
AMP/04 |
AmCross |
GRC |
Addalachchenai - distribution improvement & connection to resettlement in Alamkulam, Katchana, Oluwil, Palamunai & Sammunagar |
Connection from Kondawattuwana Irrigation tank laying of transmisson to resettlement areas in Alamkulam, Katchana, Oluwil, Palamunai & Sammunagar |
II |
| 3 |
AMP/05 |
AmCross |
GRC |
Alayadiwembu distribution improvement & connection to resettlement in Kannegipuram, Sagamam & Norochchlai |
Not finalized yet. |
II |
1.11 |
NWSD&B is in the process of providing the necessary inputs with regard to project implementation. |
| 4 |
AMP/14 |
AmCross (46.6%) |
GRC |
Akkaraipattu pipe scheme augmentation |
Augmentation of Akkaraipattu pipe scheme to connect from Kondawattuwana Irrigation tank. |
III |
2 |
AmCross is also agreed to provide their funds (71 Km worth of 2 million US$), proposal has been forwarded to their HQ (Washinton) for approval & this is also joint with Ampara 3 & 4. |
| GRC (53.3%) |
 |
2.2 |
Project proposal for GRC (80 Km and worth of 2.28 Million US$)) has been approved, Project Agreement has been finalized with SLRCS/GRC and NWSDB and signed on 14th July 2006. Agreement for Consultancy services is also under finalization, |
| 5 |
AMP/15 |
Committed by IFRC |
 |
Pottuwil pipe scheme (New scheme) |
Connection of new network of water supply in Pottuwil town, to attend 45,000 beneficiries from Rottal Irrigation tank. |
III |
5.4 |
The project depends on the USAID feasibility study for water sources and ground water.The report has been forwarded to RCM & with their comments, now they in process of investigation for Ground Water Sourses. |
| 6 |
AMP/19 |
Committed by IFRC |
 |
Rehabilitation of water treatment plant Samanthurai, Ampara District. |
Upgrading of equipment in water treatment plant of Samanthurai, Amapra District. |
 |
0.2 |
Project proposal approved, Project Agreement was not signed, 2 different tender process done and quotations received are over budget., Budget reweive is on progress and NWSDB is work on it. |
| 7 |
AMP/20 |
Committed by IFRC |
 |
Sewerage treatment plant Kalmunnai |
Construction of water treatment plant in Kalmunnai. |
 |
To be decided |
NWSD&B has to inform the necessity of this project. |
| 8 |
Out side MOU |
GRC |
GRC |
Community based project Wadinagala & Kiwulegama |
Rural water supply and improvement of Sanitation in Wadinagala & Kitulawa areas. |
 |
0.35 |
Design is completed by NWS&DB. Tendering will be take place soon. Community organizations are in process of formulating. |
| District Total |
18.26 |
 |
| 8 |
Galle |
GAL/1 |
IFRC |
NWSD&B |
Extension of pipes to resettlement areas. (Including a separate scheme for Galagoda) |
Connecton from existing main water scheme in Galle Road to resettlement areas designated by Government. |
II |
1.73 |
Implementation is in progress, 4 sites have been completed & payment was done for have been received for 7 more sites are under implementation, The project has to be completed by the end of June 2007. Payment has been done for 3 site. |
| 9 |
GAL/2 |
ARC & FRC have been comitted. |
 |
Ground water investigation, Rural water supply systems, Dug wells in affected areas where with out drinking water suppply. |
Supplying of water bowsers, water tanks, clenning and rehabilitation of wells, rehabilitation of damaged wells and latrines in Rural areas. |
II |
0.6 |
Project proposal ready to be submitted, Ground water investigation by IFRC is in progress, Drilling of tube wells for 10 sites is in progress 9 have been completed by now. 8 gives good yield (more than 100L/min). NWSD&B is in
the process of organizing CBOs & providing water facilities to the housing sites covered by this particular project. The project has to be completed by the end of June 2007. |
| 10 |
GAL/6 |
Initially IFRC was agreed to fund for this project |
 |
Dedicated pipelines from Ambalangoda - Balapitiya pumps |
 |
II |
0.5 |
Project proposal will be ready by end of September. |
| 11 |
GAL/10 |
 |
 |
Replacement to Wakwella to Beekka transmisson. |
Replacement of 7 kilometers of main transmisson pipeline from Wakwella to Beekka. |
II |
2.5 |
Project proposal will be ready by end of September. |
| District Total |
5.33 |
 |
| 12 |
Hambantota |
HAM 01 |
ARC |
SLRCS Hamb. Branch |
Implementing Rainwater harvesting systems in schools and communities. |
Rainwater harvesting system for 9 schools, 7 in Hambantota and 2 in Tangalle divisions and communities in all divisions. |
  |
0.06 |
Project completed. Final technical report by NWSD&B is on preparation. |
| 13 |
HAM 02 |
ARC |
ARC |
Moraketiara water supply project |
Installation of pumps, pipe laying work and construction of treatment plant in order to provide 120 M3 /d to Moraketiara |
 |
0.3 |
Project proposal is done, But this project is related to HAM 05 and the project will finalize on 18th July with SLRCS, ARC & NWSD&B. |
| 14 |
HAM 03 |
ARC |
NWSD&B |
Chlorination project |
Provide chlorine tanks to Tangalle and Ambalantota treament plants. |
 |
0.01 |
Project completed. |
| 15 |
HAM 04 |
ARC |
 |
Water supply connection to Hathigala |
Domestic water supply includes Iron removal plant, pumps, distribution lines, housing connection, feed water reservoir and peak flow storage removels. |
 |
0.2 |
Completed |
| 16 |
HAM 05 |
ARC |
 |
Water supply connection to Seenimodara |
Domestic water supply includes Iron removal plant, pumps, distribution lines, housing connection, feed water reservoir and peak flow storage removels. |
 |
0.48 |
Completed |
| District Total |
1.05 |
 |
| 17 |
Jaffna |
JAF/02 |
IFRC |
IFRC |
Connection of water supply to resettlement areas. |
Connection of water supply to resettlment areas from Point Pedro to Valveddiththurai (for tsunami victims) |
II |
1.7 |
TOR & RFP for Consultancy services are ready, 3 party agreement, not yet signed as it was not finalized by IFRC. The project is planned to be completed by end of May 2008. |
| 18 |
JAF/03 |
Committed by IFRC |
 |
Sanitation facilities to resettlment areas. |
Providing basic sanitation facilities to resettlement areas from Point Pedro to Valveddiththurai (for tsunami victims) |
II |
0.5 |
Design stage by NWSD&B |
| 19 |
JAF/08 |
Committed by IFRC |
 |
Rural water supply, Jaffna |
Investgate and assess (well) water supply and hygiene interventions in Western Jaffna Islands. |
 |
0.4 |
Project proposal is ready to be submitted, Design has been done & it has been exceeded the estimates, Further discussion are in progress with relation to budget. NWSD&B has requested in prioritizing the project. |
| District Total |
2.6 |
 |
| 20 |
Matara |
MAT/02 |
AmCross |
AmCross |
Pipe laying to resettlment areas including Weligama - Midigama areas. |
Connection from existing water scheme in Weligama District Division to resettlment areas designated by Government. |
II |
1.94 |
Consultant has started work in site 08 sites & 4 have been completed by NWS&DB (20 million worth work which has been done by NWS&DB is checking by consultant) |
| 21 |
MAT/03 |
Committed by IFRC |
|
Ground water assessment, rehabilitation of Dug wells and Rural water supply systems in affected areas where with out drinking water suppply. |
Supplying of water bowsers, water tanks, clenning and rehabilitation of wells, rehabilitation of damaged wells and latrines in Rural areas. |
II |
0.06 |
All work identifed by this project will be included in Matara 2 project. |
| 23 |
MAT/04 |
AmCross is verbally agreed. (initially IFRC was agreed to fund for this project) |
 |
Pipe scheme, Secondary pumping for hilly areas (Kamburugamuwa - Mirissa. |
Construction of new pump house, elevated tower and distribution network to cover the unserviceable areas and the low pressure area in Kamburugamuwa. |
II |
1.07 |
NWSD&B is interested in MAT/05 than MAT/04 to be started. Funding will be finalized with in 6 weeks time as it has to get the approval from AmCross HQ-Washington. |
| 24 |
MAT/05 |
Committed by IFRC |
 |
Improvement of distribution to Weligama area. |
Replacement of AC main transmission from Halalla treatment plant to Weligama - Kottegoda service reservoir. |
II |
3 |
IFRC has been prepared the Project proposal & it will be submitted to TC by 15th July. Design part will be done by NWSD&B. |
| 25 |
MAT/06 |
French RC |
 |
Distribution improvement to Kudawella area. |
Construction of new pump house at existing Dickwella - Batheegama reservoir site, supply and installation of pumps and control equipment. |
II |
0.06 |
FRC is taking over the Replacement of a 2.3 km Main Water Supply Pipeline between Dickwella Ground Reservoir & Naigala Water Tower. Project Proposal will be submitted to TC on 18th July. |
| 26 |
MAT/07 |
 |
 |
Distribution improvement of Matara WSS and replacement of Nadugala - Uyanwattamain pumping line |
Improvement of a new main transmission from Nadugala to Uyanwatta, replacing the existing CI transmission. |
II |
1.5 |
Concept paper has been approved by AmRC HQ. But NWSD&B has informed that the project is not a priority for this year (Next year 2007). |
| 27 |
MAT/10 |
Committed by IFRC |
 |
Replacement of AC transmission from Devinuwara & Dikwella - III |
Replacement of AC main transmisson from Devinuwara and Gandara. |
II |
5 |
The project is on hold for 2007. Estimate has come down. NWSD&B is in the process of finding funds for some stages. |
| District Total |
12.63 |
 |
| Sub Total |
39.87 |
 |